Mount Gibson to Start T1 Production in September
Australia's Mount Gibson Iron Limited announced on Jul 17 that first ore production from the T1 hematite deposit at the Tallering Peak iron ore mine is scheduled to commence in September 2013. Tallering Peak iron ore mine is located 260km east of Geraldton and 1km east of the current T6 main pit.

Following detailed study, the company has estimated Probable Ore Reserves for the T1 deposit totalling 801,000 tonnes grading 61.0% Fe, using a 55% Fe cut-off. T1 production is expected to conclude in mid 2014.